Blueprint - Phased Implementation Plan

Bay Area Transportation Blueprint --
Phased Implementation Plan

Appendix 1 - Transit Investment Package by Corridor

Phase 1- Planning and Engineering (Fund Sources in Millions)  Corridor Subarea Other  
Fremont-South Bay I-80 Peninsula San Francisco I-880 I-580 I-680 Route 4 Routes 92 and 84 Golden Gate Santa Clara Lifeline Transit Rapid Bus and Lifeline Transit Operations TOTAL
Torlakson Budget Request $7 $2.5 $3.5 $6 $7 $0.25 $7   $0.25         $33.5
Additional Budget Request                 $3 $7 $7
Northwest Pacific (NWP)
    $17
STIP         $4                 $4
Phase 1 Subtotal $7 $2.5 $3.5 $6 $4 $7 $0.25 $7 $3 $7.25 $7 N/A N/A $54.5
Phase 2- Initial Implementation (Fund Sources in Millions)  Corridor Subarea Other  
Fremont-South Bay I-80 Peninsula San Francisco I-880 I-580 I-680 Route 4 Routes 92 and 84 Golden Gate Santa Clara Lifeline Transit Rapid Bus and Lifeline Transit Operations TOTAL
BART to Warm Springs Commuter Rail
BART Connection
Capitols
Intercity Rail
Rapid Bus1 Caltrain Express
and Upgrades
I-280
Rapid Bus1
Muni Metro
Central Subway
BART - Oakland
Airport Connector
Rapid Bus1 ACE Commuter Rail Rapid Bus1 Rapid Bus1 Rapid Bus1 Rapid Bus1 Rapid Bus1 Vasona LRT and Measure B Shortfall Rapid Bus1
State Funds Requested   $59
($35 ROW / $24 Service)
$89 $11 $133
($127 Caltrain Express / $6 other upgrades)
$8 $180 $39 $3 $36 $4 $10 $5 $5 $8 $192
($27 Vasona LRT / $165 Measure B shortfall)
$5 $9 $210
(STA)
$1,006
New Starts $227           $300                         $529
(FY 2015, $529 total)
FTA Bus Discretionary       $23   $15     $6   $8 $19 $11 $9 $16   $11     $118
County Sales Tax $166
(Alameda Measure B proposed)
$96
(Santa Clara Measure A/B)
          $66
(Alameda Measure B proposed)
                      $328
RTIP             $50                         $50
ITIP     $98             $46                   $144
Other $151
(Resolution 1876 repayment)
            $25
(Port of Oakland)
                    $175
(tolls)
$351
Phase 2 Subtotal $56 $155 $187 $34 $133 $23 $530 $130 $9 $83 $12 $29 $16 $14 $24 $192 $16 $9 $385 $2,526
TOTAL (Phases 1 and 2) $553 $155 $189.5 $34 $136.5 $23 $536 $134 $9 $89 $12 $29.25 $23 $17 $31.25 $199 $16 $9 $385 $2,580.5
Phase 3- Future Upgrades Corridor Subarea Other
Fremont-South Bay I-80 Peninsula San Francisco I-880 I-580 I-680 Route 4 Routes 92 and 84 Golden Gate Santa Clara Lifeline Transit Rapid Bus and Lifeline Transit Operations
 
  • BART to San Jose
  • Capitols commuter service frequency upgrades
  • New Transbay Terminal
  • TBD by Southern Crossing Study
  • Caltrain Electrification
  • Caltrain Downtown Extension
  • Third Street Muni Metro Phase 3
  • Muni Metro Geary and North Beach
  • TBD
  • BART to Livermore
  • ACE commuter service frequency upgrades
  • Additional rapid bus service
  • BART to Antioch
  • ACE extension in Dumbarton Corridor
  • NWP rail
  • Light Rail Extensions
  • TBD
  • TBD

NEXT: Appendix 2 - Highway Investment Package

Back to Table of Contents