New Bay Bridge East Span Tower Peeks Above Yerba Buena Island
Photo:
Barrie Rokeach
PRESS RELEASE:
Four Million Pounds of Steel to Be Hoisted in Pre-Holiday Construction
Latest
Sections Will Bring SAS Tower to 71 Percent of Final 525-Foot Height
Oakland,
December 15, 2010... The holidays will come early for
the Bay Bridge as the third set of tower sections for the iconic Self-Anchored
Suspension Span (SAS) are placed during a round-the-clock lift scheduled
to begin this morning. These sections will bring the tower up to nearly
three-quarters of its final 525-foot-tall height.
The latest set of
four tower sections arrived in the Bay Area on December 13. The tower
is made up of four independent legs, each of which is composed of five
vertical sections. The third set of tower sections will bring the tower
up to 374 feet tall, just shy of the original East Span’s high
point of 388 feet. The new set of tower segments are 101.7-feet-tall
and each one weighs approximately 1.1 million pounds. While the tower
will rise nearly 38 stories above the bay, that is only 71 percent
of the tower’s final height,
already making it taller than Coit Tower (210 feet), the Campanile
at U.C. Berkeley (307 feet) and the Tribune Tower (310 feet).When
completed, the SAS will take its place on the list of iconic Bay
Area landmarks.
Two strand jacks will hoist each section about 40 stories
into the air, so that each segment can be moved into the erection tower
just above the first two sections of the tower. Once the third section
is lowered into place, crews will bolt the third and second sections
together using splice plates.
Crews will work around the clock, using
two 12-hour shifts, to erect all four tower sections; it takes approximately
30 hours to lift, place and bolt each section and then lower the strand
jacks into position before the next section can be lifted. The work
is expected to be completed during the week of December 19.
Crews placed
the first tower sections onto the foundation in July 2010, and the
second set in October 2010. The arrival of the final group of tower
sections is expected in February 2011.
See also:
December 14, 2010
After 28 days crossing the wintery Pacific Ocean from Shanghai, the
third shipment of tower sections for the self-anchored suspension
span (SAS) of the new San Francisco-Oakland Bay Bridge East Span
passed under the Golden Gate and into San Francisco Bay on December
13. Also loaded aboard the Zhen Hua 19 were two more steel deck sections
for the new span, and first pieces of the bicycle/pedestrian path
to be delivered to the job site.
The SAS tower is actually comprised of four individual legs, each
of which is made up of five vertical sections, or lifts. This third
lift contains four legs that are 102-feet-tall and weigh 551 tons each.
Once this third installment is placed, the tower will stand 374 feet
tall – 40 feet above the high-point of Yerba Buena Island, and
nearly three-quarters of the way toward its final height of 525 feet.
Contractor American Bridge/Fluor plans to start the erection of these
tower sections as early as Wednesday, and to work around the clock
until complete, in time for Christmas. The painstaking process involves
tilting each leg from horizontal to vertical on a specially-designed
barge positioned at the tower’s base, and then hoisting the legs
over 400 feet into the air before lowering and bolting them atop the
tower. (See
previous story about lifting process.)
Meanwhile, the SAS road decks have been taking shape since February,
with 18 deck sections – nine eastbound and nine westbound – already
in place. The deck sections that arrived with yesterday’s shipment
are each almost 160 feet in length, and weigh over 1,000 tons each.
When the bridge opens, there will be 28 deck sections in total.
The Bay Area Toll Authority (BATA) — along with Caltrans and the
California Transportation Commission — is part of Toll Bridge Program
Oversight Committee (TBPOC), which has been overseeing the seismic retrofit
of state-owned toll bridges in the Bay Area, including the Bay Bridge.
BATA is also responsible for collecting bridge tolls and funding the
retrofits.
—
Karin Betts
Previously: