February/March 2007
New Bay Bridge East Span Milestone: Skyway Deck Complete
Closing of One Chapter and Beginning of Another as Work Advances
on Tower Segment

Crews delicately hoist a massive 750-ton segment — the last of 452
precast concrete deck pieces — into place on the new East Span Skyway.
The banner reads: “Skyway Project — Final Segment: Congratulations
to everyone involved!”
(Photos: Noah Berger)

The 452 concrete deck segments were “match-cast” to fit precisely
against each other.

The last Skyway deck section makes the 80-mile journey
from Stockton to the construction site by barge.

Jutting a mile into the Bay, the Skyway’s twin decks stand ready
to meet up with the self-anchored suspension span.

A basketball-court-sized section of the foundation for the East Span tower
passes through the Panama Canal.
MTC’s Bay Area Toll Authority (BATA) and Caltrans summoned
the media to the Delta city of Stockton in December to witness
a historic event: the shipping by barge of the last of the
452 precast concrete segments that make up the twin decks of
the Bay Bridge’s new East Span Skyway. A couple of days
later and some 80 miles downstream, the media looked on again
as crews lifted the banner- and flag-festooned 750-ton segment
into place 100 feet above San Francisco Bay.
The shutdown of the Stockton
fabrication yard marks a key milestone both for the bridge
workers and for the Toll Bridge Program Oversight Committee
(TBPOC), made up of representatives from Caltrans, BATA and
the California Transportation Commission. “It’s
the closing of one chapter and the beginning of another for
this monumental project,” said BATA Deputy Executive
Director Andrew Fremier, alluding to the challenging next
phases of construction.
For the past three years, the now-silent Stockton yard was
a beehive of activity as roughly 260 bridge builders working
for Caltrans and the joint venture contractor, Kiewit-FCI-Manson
(KFM), processed 130,000 cubic yards of concrete and 31 million
pounds of steel. Custom-made equipment was used to “match-cast” every
piece to fit precisely with adjoining pieces. Those sections
now make up the roadway of the 1.2-mile-long Skyway — the
longest portion of the new East Span.
Although the road deck is in place, the Skyway contract is
not scheduled for completion until
the end of 2007. Between now and then, Caltrans will place
the final concrete overlay, install electrical and mechanical
systems, and finish the bike and pedestrian path.
The Skyway
now ends abruptly in midair a half-mile from Yerba Buena
Island, but eventually will link to the bridge’s
crowning element, a stunning suspension span with a 525-foot
tower. Piles for the tower’s marine foundations were
drilled 196 feet below the waterline to anchor in bedrock.
Crews are now in the process of attaching a massive steel footing
box — which weighs 2,100 tons and would cover a basketball
court — to the piles at water level and sealing it with
concrete to create the tower’s foundation. Fabricated
in Texas, the footing box is so immense that the only transport
option was via barge through the Panama Canal.
Up ahead in 2007, Yerba Buena Island will be a hub of activity
as construction proceeds on the
span’s western land-based foundations, as well as on
a temporary
structure south of the existing bridge. Dubbed the “south-south
detour,” this structure will carry both directions of
diverted bridge traffic when the time comes to close the existing
roadway near the tunnel in order to connect the new span at
this location. The tall columns that will support the
temporary viaduct — a double-deck steel truss structure — are
already 50 percent complete and look like out-of-place Greek
Doric columns on the banks of
the island. Halfway around the
world, in South Korea, skilled
metal workers are fabricating the
temporary steel viaduct, which will be shipped across the Pacific.
The suspension span’s permanent steel deck sections,
along with the tower and cables, will be fabricated near Shanghai,
China, and then erected (or in the case of the cables, hung)
starting in 2009.
When complete, the new East Span will boast the world’s
longest single-tower, self-anchored suspension bridge (or SAS).
A single, continuous main cable will run over 4,500 feet, linking
the eastern edge of the SAS deck to the tower top, then descending
to the western edge at Yerba Buena Island, where it will loop
around the bottom of the deck before again soaring to the top
of the tower and returning to anchor inside the deck on the
other side. The new East Span is expected to fully open to
traffic in 2013.
— Karin Betts
Contents