 |
|
|
Home
About MTC
News
Jobs & Contracts
Meetings & Events
Get Involved
Services
Library
Maps & Data
Funding
Planning
Projects
Legislation
Links
|
April/May 2003
Project Update
Fish-Friendly Bridge Project Forges Ahead
Construction crews are nearing the end of the first phase of foundation work for the new
Benicia-Martinez Bridge. By July, they will have driven approximately 100
eight-foot-diameter steel piles — each up to 164 feet in length — deep into the
waters and bedrock of the Carquinez Strait. The next step will be to drill deeper still,
through the hollow center of the piles, anchoring the foundations as much as 300 feet below
the surface of the water.
Crews are logging long hours driving piles for the new
Benicia-Martinez Bridge.(Photo: Caltrans)
The crews are playing catch-up, having been idle for several months last winter while state
and federal environmental resource agencies, Caltrans and MTC — in its role as the
Bay Area Toll Authority — looked for a way to protect fish in the strait from lethal
sound waves caused by the pile-driving.
In early February, the go-ahead was given to use an ingenious “bubble curtain,”
generated by large air compressors, to dissipate the noise and damaging shock waves.
Several weeks of testing showed that the Jacuzzi-like bubble shield was working as hoped.
The delay and extra expense incurred in solving the environmental problem as well as other
unexpected factors — including difficult site conditions and design modifications for
the bridge’s superstructure — could raise the price tag by $250 million,
bringing the total estimate to over $900 million.
Rod McMillan, MTC’s manager of Bridge and Highway Operations, noted that the
escalated costs could be paid for in part out of contingency funds in the toll bridge
program. Funding also could come from re-configuring other bridge projects not yet under
way that, like the Benicia-Martinez Bridge, are financed by revenues from the toll increase
approved by the region’s voters in 1988. “We believe we can make the necessary
adjustments to fund most of these latest cost increases,” McMillan said. A
contribution from a possible new bridge toll increase being pursued by state Sen. Don
Perata also could help (see story).
Associated projects also are moving ahead. Work crews are pouring concrete for the new
Interstate 680/I-780 interchange, widening northbound I-680 at the Marina Vista interchange
and erecting steel framing for a new, expanded toll plaza on the south side of the Benicia
Bridge. The existing span — which was retrofitted by Caltrans in 2002 — will be
converted to four southbound-only lanes plus a new bicycle and pedestrian pathway by early
2007, following completion of the new five-lane bridge in 2006.
— Réka Goode
Contents
|
|
|
|
|