|
Project Updates: Bridges in
Brief
On a sunny morning in early July, groundbreaking ceremonies at the Benicia-Martinez
Bridge officially launched construction of a new span to link Contra Costa and Solano
counties. The $385 million bridge is one of several major Bay Area bridge projects in the
works that are mandated and financed by Regional Measure 1 (RM1), the 1988 voter-approved
ballot measure that raised tolls on the region's seven state-owned toll bridges to a
uniform $1. (In 1998 a $1 surcharge for seismic retrofit was added to bridge tolls.) All
three RM1 projects described below are scheduled for completion in 2003.
The current Benicia-Martinez Bridge spanning the Carquinez Strait will
be widened to four lanes of traffic southbound, plus a two-way bicycle/pedestrian lane. The
new causeway, east of the existing one, will carry five lanes of northbound traffic,
including a slow-vehicle lane. In order to accommodate the new bridge approach and an
expanded toll plaza -- relocated to the Contra Costa County side -- freeway interchanges at
either end of the bridge will be reconstructed as well.
In the next few months, construction contracts will be awarded for a new
Carquinez Bridge, a twin-tower suspension span to replace the 72-year old,
westbound steel truss span. The new bridge will include a bicycle/pedestrian lane, and the
existing eastbound structure will be retrofitted.
Photo: Caltrans
Computer-enhanced photo of the Carquinez Bridge showing the new
west-bound span. (Click image to enlarge)
The San Mateo-Hayward Bridge project will complete the work to widen
the bridge and its approaches from two to three lanes in each direction. A new span will be
built north of the existing low-rise, trestle section and the eastern approach widened to
three lanes. (The high-rise portion will remain unchanged.) The project passed an important
milestone recently when the Bay Conservation and Development Commission approved Caltrans'
plans, with the proviso that a bicycle shuttle across the span be provided and the Bay
Trail at the Hayward end of the bridge be improved. (The design includes a
pedestrian/bicycle overcrossing of the eastern approach for safer access to the shoreline
path.)
Design of another bridge project -- the new eastern span of the San
Francisco-Oakland Bay Bridge -- is stalled due to the U.S. Navy's refusal to
permit necessary geotechnical test drilling on Yerba Buena Island (YBI). The Navy opposes
the span's northern alignment, which is the basis of the design selected by MTC acting as
the Bay Area Toll Authority. Without test drilling, Caltrans cannot finalize the design,
now 65 percent complete for the long viaduct section of the bridge but only 30 percent
complete for the section over YBI. Caltrans estimates the delay has cost $50 million and
added nine months to construction.
Gov. Gray Davis has written to Secretary of the Navy Richard Danzig, urging that the
drilling be permitted, stating, "...As Governor my paramount concern is public
safety...Every day of delay in completing this seismic safety project courts another
disaster."
In the meantime, MTC has approved several additional design features recommended by the
Bay Bridge Design Task Force and the Engineering and Design Advisory Panel. The commission
approved equipping the new span with motion detectors to measure response to future
earthquakes; using "earth fill" instead of shallow piers at the Oakland touchdown; and
constructing seven rest stops on the bicycle/pedestrian path.
-- Réka Goode
Contents
|