September 2004
Political Deadlock Threatens to Slow Bay Bridge East Span
Project
Towering cranes outline the path of the new East
Span’s causeway section. (Photo: Bill Hall, Caltrans)
Delays Could Push Cost Overruns Even Higher
A dramatic scene unfolded over the
region’s waters in late July
as giant hoists delicately lifted the
first 400-ton steel-reinforced concrete
deck section into place on the new
East Span of the San Francisco-Oakland
Bay Bridge.
Another drama — of the political kind — played out in August when Governor
Arnold Schwarzenegger unveiled his proposal for dealing with the cost overruns associated
with the state’s Toll Bridge Seismic Retrofit
Program, and especially the East Span project.
With construction on the causeway portion of the
East Span well under way and the September 30 deadline
fast approaching for the state to accept or reject
the lone bid for building the final portion of the
bridge — a self-anchored suspension span — the
issue of how to cover the overruns has come to a
head.
Governor Eyes Toll Revenues
The governor sparked a seismic event of his own at the August 16 press conference when he
proposed a November 2004 measure asking Bay Area voters to divert money from the new
Regional Measure 2 (RM 2) program to pay for the $3.2 billion in cost overruns.
At the same time, the governor called for an independent
audit team “to determine why
this bridge took so long to plan and construct,” as well as to “perform a
complete fiscal analysis of the dollars spent” to date. The third leg of the
governor’s three-part solution involved legislation to transfer responsibility for
overseeing the Toll Bridge Retrofit Program from Caltrans to MTC, while providing the
regional agency “with all of the tools to fix
the problem now and in the future.”
Passed by Bay Area voters in March 2004, RM 2 raised
tolls on the region’s seven
Caltrans bridges to $3, effective July 1, 2004, with
proceeds from the $1 increase earmarked for public
transit and highway projects to ease traffic congestion
in the bridge corridors and to provide transbay commuters
with more alternatives to driving.
“The argument that we (Bay Area residents) bear the cost by ourselves is ludicrous.
It is not in keeping with tradition or history,” state Senator Tom Torlakson (D
– Antioch) told the SF Chronicle in the wake
of the press conference.
East Span Bid in Limbo
In the two weeks between the governor’s announcement and the close of the state
Legislature’s 2003–2004 session, MTC and the Bay Area legislative delegation
quickly mobilized to defend RM 2, countering the Governor’s
proposal with Assembly Bill 2366 (spearheaded by
Assemblyman John Dutra, D-Fremont, along with incoming
state Senate President Pro Tem Don Perata, D-Oakland).
The bill called for an interim solution, whereby
the state would accept the construction bid for the
suspension span while MTC, acting in its role as
the Bay Area Toll Authority (BATA), would shift toll
reserves and refinance existing toll bonds to cover
immediate costs.
Suspension span foundations at Yerba Buena Island
near completion. (Photo: Bill Hall, Caltrans)
The goal was to buy time to allow BATA and the state to take a measured look at the
root causes of the overruns and to develop an equitable solution that draws on federal,
state and local funding sources.
While the Perata/Dutra bill passed
the Senate, it was never brought to
a vote in the state Assembly. Schwarzenegger’s
ballot measure also was rejected, leaving
the bid for the suspension span in
limbo.
“Every day we delay the East Span project translates to higher costs,” said
MTC Spokesman Randy Rentschler. That point is bolstered by a just-released report
commissioned by MTC. Prepared by Bechtel Infrastructure Corporation, the report
found that seeking new construction bids for the suspension span, or shifting
to a more conventional cable-stayed design, could delay the opening of the new
East Span by as much as four years (to the year 2015) and could lead to inflationary
cost increases of as much as $310 million.
Public Safety at Risk
Incalculable is the risk to public safety of prolonged travel on the seismically weak old
East Span, which fractured in the 1989 Loma Prieta earthquake (with an epicenter 60 miles
away).
“We can’t afford to start from scratch,” Rentschler said, noting that the
skyway has been under construction since January 2002 and that crews have nearly completed
the foundations on Yerba Buena Island for the self-anchored suspension span. Moreover, he
said, redesigning a portion of the bridge at this late stage could call into question the
earthquake readiness of the entire structure — an
ironic twist given that seismic safety has been the
primary goal of the project from the outset.
— Brenda Kahn
Contents
- Bay Bridge East Span
- In Brief
- Project Update