November-December 2009
Diary of a Dramatic Construction Operation
Crews Race Against Time to Install Last Piece of
Bay Bridge Bypass and
Repair Failed Eyebar

In this aerial view taken early Saturday
morning during Labor Day weekend, the old deck piece has
been rolled out of the way (to the right), and the replacement
piece (to the left) — and
last link to a bypass — is ready to roll in. (Photo: © 2009 Barrie Rokeach)
A series of loud metallic pops in the late afternoon of Friday,
September 4, was music to the ears of the Caltrans and Bay
Area Toll Authority (BATA) officials perched at a strategic
location on Yerba Buena Island and monitoring the movement
of a massive deck section of the old East Span of the Bay Bridge.
The
noise indicated that after nearly 24 hours of preparation that
had commenced with the bridge closure the night before, the
3,200-ton, 300-foot deck section was finally free of its moorings
and was ready to roll. Once it started to move on skids reportedly
greased with common dish soap, the double-deck piece slid out
with relative ease and speed, assuming its resting position
150 feet above the ground by early Friday evening of Labor
Day weekend. Much on-the-scene preparation and angst went into
that climactic moment, and not everything went according to
plan when it came to amputating a chunk of the 73-year-old
span.
“When you open up an old bridge, you find out a
few things. It has a few secrets to give up. We found a few
of them today,” Caltrans
Toll Bridge Deputy Program Manager Brian Maroney said that
Friday, midway through the process. “We found some extra
steel that was welded and needed to be cut.”
According
to Maroney, the engineers were dealing with 80-year-old plans
that weren’t necessarily in sync with shop drawings
of a similar vintage that were inked on linen. “The old
shop drawings are works of art; they’re pieces of history,” he
said. Adding to the bridge’s mysteries, still more changes
were made in the field during the Depression-era construction,
and they weren’t always well documented.
Engineers also
had to prescribe measures to ensure that the remaining portions
of the old bridge wouldn’t tilt precariously
into the “maw,” the cavernous hole left when the
deck section was removed.
Fortunately, the engineers had a powerful
ally on their side in the form of the prime contractor on the
job, C.C. Myers Inc. Based in Rancho Cordova, Calif.,
the firm has carved out a reputation for
tackling “impossible” construction projects under
extreme time pressures, including the demolition and roll-in
replacement of an upper-deck segment on the same bridge over
Labor Day weekend in 2007.
Roll In: Hurry Up and Wait
With the most challenging phase
of the procedure completed, crews on Saturday morning (September
5) turned their attention to the rolling in of the last piece
of a detour structure. The temporary detour will carry traffic
to and from the Yerba Buena Island tunnel over the next several
years while the new East Span of the Bay Bridge is connected
to the mouth of the Yerba Buena Island tunnel. The Skyway portion
of the new East Span, consisting of a pair of sleek road decks
stretching more than a mile westward from the Oakland shore,
is already complete. Closing the gap between the Skyway and
the Yerba Buena Island tunnel will be a striking self-anchored
suspension span with an iconic tower rising 525 feet above
the water.
All day Saturday it was hurry up and wait as crews
prepped the bypass piece and then started and stopped the roll-in
procedure a couple of times. By lunchtime on Saturday, the
piece appeared to have slid halfway in, a position it maintained
until the late afternoon, at which point it traversed the last
stretch smoothly and nearly silently, with a swift pace that
belied its 3,600-ton weight.
Just as onlookers were celebrating
the successful completion of the tricky roll-out/roll-in procedure
and the impressive closure of the gaping hole in the double-deck
structure, Caltrans delivered stunning news at a Saturday evening
press con-ference: Inspection crews had detected a significant
fracture in an “eyebar” piece
of the cantilever structure farther down the line on the old
East Span. The presence of rust indicated that the break had
been there for some time and was not caused by the weekend’s
trauma to the bridge.
The fracture was not entirely surprising,
given the span’s
age; in fact, it underscored the urgent necessity for replacing
the old East Span, which failed in the 1989 Loma Prieta earthquake
along one section.
Fractured Eyebar Triggers Scramble
The discovery of the broken
eyebar set in motion a scramble to design, commission and install
a fix. Stinger Welding Inc. in Arizona was able to fabricate
crucial steel repair components in a day and ship them on a
charter plane that landed in Oakland by midday on Sunday. Underscoring
the time pressures, the flatbed truck that hauled the 18,000
pounds of steel from the airport to the bridge was escorted
by the CHP.
“An eyebar is a tension member; it is very
important to the structure, which is the reason for the urgency
to repair it now while the bridge is closed,” Mike Forner,
Caltrans’ district
division chief for the San Francisco-Oakland Bay Bridge, said
at a late-afternoon press briefing on Sunday.
“It has
been an incredible effort to get fabricators together and the
design done and all the materials here during Labor Day weekend
while most people are out enjoying barbecues,” said
Caltrans spokesperson Bart Ney at the press briefing.
While
the eyebar repair took center stage Sunday and Monday, other
important work was going on as well, most notably a major reconfiguration
of the bridge’s toll plaza (see story) that was timed
to coincide with the rare bridge closure. Crews also were striping
lanes, painting, hooking up the utilities that traverse the
bridge, installing traffic barriers and the like.
All day on Monday, Labor Day proper,
the region held its collective breath, wondering if the work
would be done in time for the planned reopening of the bridge
at 5 a.m. on Tuesday morning. Keeping track of the progress
wasn’t hard: News outlets
covered the unfolding drama nearly continuously, while Caltrans
public information officers posted updates on Twitter at frequent
intervals. And BATA had six stationary still cameras as well
as a stationary video camera trained on the bridge construction
zone, delivering fresh images to the Web 24/7.
At a 6 p.m. press
conference on Monday, officials confirmed commuters’ worst
fears: Contractors could need another full day to complete
the eyebar repairs, pushing the opening back 24 hours to 5
a.m. Wednesday. But thanks to the perseverance of the crew
of ironworkers and other craftspeople who struggled on through
the night, commuters woke up Tuesday morning to a pleasant
surprise: starting
at 6:10 a.m., the CHP began to remove barriers on the approaches,
and by
7 a.m., the bridge was fully open — just two hours beyond
the original planned opening time.
It was yet another dramatic
twist in a dramatic weekend. End of story? Not quite. Some
seven weeks later, high winds appeared to trigger vibrations
that snapped a key element in the eyebar repair assembly, causing
debris to fall on the bridge deck. Officials quickly shut down
the bridge once again, and kept it closed while they reengineered
and reinforced the repair. While the repairs took longer than
expected and the closure stretched over a work week, the region’s
commuters adjusted quickly and flocked to transit, pushing
BART ridership to its highest daily levels ever.
Slowing for
the “S” Curve
Drivers also have been adjusting to
the pronounced “S” curve
that is a necessary feature of the new bridge bypass leading
to and from the Yerba Buena Island tunnel. The speed limit
on this nearly half-mile section has been set at 35-40 mph,
down from the 50 mph in force elsewhere on the bridge. The
stretch has been a navigational challenge for those motorists
and truckers who fail to obey the new speed limits, and has
been the scene of a number of accidents. Caltrans has been
installing signage and pavement markings while also undertaking
an informational campaign to alert
drivers to the new configuration, which
will be in place for the next four years,
until the striking and seismically sturdy new East Span of
the Bay Bridge completes its march toward the Yerba Buena Island
tunnel.
— Brenda Kahn (with field reports by Karin Betts)
Contents