East Span Replacement
MTC Staff Recommendations to the Bay Bridge Design
Task Force
June 17, 1998
Return to main Bay Bridge
page
Pursuant to Senate Bill 60 (Kopp), signed into law by Governor Wilson in August
1997, this memorandum presents MTC staff recommendations on the design and
amenities of the new eastern span of the San Francisco-Oakland Bay Bridge and
the associated extension of the $1 seismic retrofit toll surcharge in effect
on the region's state-owned toll bridges. Our five recommendations -- and the
requisite toll surcharge extension to pay for those with incremental cost above
the baseline bridge defined in statute -- are summarized below:
1. The new eastern span should have a single-tower
self-anchored steel suspension long span at Yerba
Buena Island with a variable depth concrete causeway
connecting the long span to the Oakland shore.
Incremental cost: $91 million
Toll surcharge extension: 9.5 months
2. The new eastern span should have a single bicycle/pedestrian
path 15.5 feet wide and 1 foot above deck level
on the south side of the eastbound deck.
Incremental cost: $50 million
Toll surcharge extension: 5.2 months
3. A decision on relocating or replacing the Transbay
Transit Terminal should be deferred until such
time as sufficient consensus has been achieved
in support of relocation or replacement of the
current facility and a complete financial plan
has been developed for the supported option.
4. The pile caps for the piers supporting the
causeway section of the new bridge should be placed
above water, but with careful attention to the
design.
5. The Bay Bridge Design Task Force should provide
continuing design oversight of the remaining design
phase for the new eastern span including, but not
limited to, the following key issues: the Yerba
Buena Island transition and possible replacement
ramps, the design of the causeway section of the
bridge, and the Oakland touchdown.
Thus, the total incremental cost associated with
our bridge design and amenity recommendations is
$141 million, which would require a 14.7 month
extension of the toll surcharge. Since SB 60 authorizes
the Bay Area Toll Authority (BATA) to extend the
surcharge up to 24 months, the staff recommendations
would leave a balance of 9.3 months ($89 million)
in reserve for the Transbay Terminal project subject
to later action by the authority.
As acknowledged in our last memo to the Task Force
on June 4, the cost of the baseline bridge is now
expected to be higher than when SB 60 was passed.
For example, Caltrans has included additional costs
in its estimate to respond to new information regarding
earthquake ground motions, and is continuing to
refine its estimate of the cost of other bridge
elements. Caltrans also has included contingency
amounts in its cost estimates prepared to date.
Under the law, any actual cost increases not covered
by these contingency amounts must be reported by
Caltrans to the Legislature for additional funding
authorization. The $89 million in reserve for future
BATA action on the Transbay Terminal is not intended
to be available to cover increases in the underlying
cost of the new eastern span.
Bridge Design Selection
After a 30 percent design competition among four
cable-stayed and suspension alternatives and intensive
deliberations over the seismic performance, architectural
excellence, and cost of the four alternatives,
the Engineering and Design Advisory Panel (EDAP)
has recommended a single-tower self-anchored steel
suspension long span for the new bridge. We recommend
that BATA support the result of the extensive engineering
and design review process it established by endorsing
EDAPs major design recommendation. The panel concluded
that the suspended long span is the best design
for the following reasons:
- The single-tower and self-anchored features
of the suspended long span represent important
advances in bridge and seismic design;
- The suspension span will involve less long-term
maintenance cost than the cable-stayed alternative;
- It features an asymmetrical design that is
not only visually appealing but allows for a
superior tower foundation and wider shipping
channel; and
- The recommended design links the new eastern
span to the Bay Areas rich tradition of suspension
bridges.
EDAP also recommended that the causeway section
of the new bridge have a minimum span length (distance
between piers) of 525 feet except near the Yerba
Buena Island transition and the Oakland touchdown,
in order to reduce the number of supporting piers.
To accomplish these longer causeway spans, EDAP
recommended that Caltrans design and bid two alternatives
for the causeway section of the new bridge: a variable
depth (arch-like profile) concrete deck and a constant
depth (level profile) steel deck. The winning low
bid would determine the construction materials
to be used.
Caltrans staff informs us, however, that this
parallel causeway design process would entail $13
million in added design cost and that their current
estimate that the steel causeway alternative would
cost $75 million more than the concrete alternative
is very likely to be borne out in the bidding process.
We defer to Caltrans' judgment and, accordingly,
recommend that EDAP's preference for longer causeway
spans be accommodated through the lower cost variable
depth concrete alternative.
Caltrans estimates that the suspension design
with a variable depth concrete causeway will cost
$76 million more than the baseline bridge defined
in SB 60, which includes an allowance for a cable-supported
long span. We recommend including architectural
lighting as proposed by the design team, which
will increase the cost by $15 million to a total
of $91 million.
1. The new eastern span should have a single-tower
self-anchored steel suspension long span at Yerba
Buena Island with a variable depth concrete causeway
connecting the long span to the Oakland shore.
Incremental cost: $91 million
Toll surcharge extension: 9.5 months
Bicycle/Pedestrian Path
EDAP recommends including a bicycle/pedestrian
path on the new eastern span. The Bay Conservation
and Development Commission, the Bay Area congressional
delegation, and the vast majority of public commenters
have supported inclusion of a path. The new Carquinez
and Benicia bridges to be constructed in the next
few years also will include bicycle/pedestrian
paths.
It is difficult to forecast use of such a facility
but, for comparison purposes, on a recent weekend
day, 5,500 pedestrians and 3,400 bicyclists used
the sidewalks on the Golden Gate Bridge. Some have
contended that building a path only on the new
eastern span makes little sense because it will
not enable users to travel all the way to San Francisco.
However, we expect that many bicyclists and pedestrians
will use the path for recreational purposes, and
the destinations of Yerba Buena Island, Treasure
Island, and even the new bridge itself will attract
these users.
EDAP recommended that bicycle/pedestrian access
should be accommodated with a single path on the
south side of the eastbound deck, with a width
and height (relative to the deck) adequate to ensure
the safety and comfort of path users and protect
the views of motorists. Caltrans and MTC staff
have concluded that a path 15.5 feet wide and 1
foot above the roadway deck will satisfy EDAPs
criteria for the safety and convenience of both
path users and motorists. We recommend that such
a path be included at an incremental cost of $50
million.
For your information, AB 2038 (Migden) would authorize
BATA to expend toll surcharge funds on a bicycle/pedestrian
path on the existing west span of the Bay Bridge.
The bill has passed the Legislature and is awaiting
action by the Governor. Pending enactment of the
bill, we make no recommendation on a west span
path at this time.
2. The new eastern span should have a single bicycle/pedestrian
path 15.5 feet wide and 1 foot above deck level
on the south side of the eastbound deck.
Incremental cost: $50 million
Toll surcharge extension: 5.2 months
Transbay Transit Terminal
SB 60 defines the third eligible amenity for toll
surcharge extension funds as the replacement or
relocation of the transbay bus terminal in the
City and County of San Francisco. In our staff
report to the Task Force and Commission last July,
we recommended that toll surcharge funds be dedicated
to the relocation of the Transbay Terminal to a
new facility at Howard and Beale Streets, which
is three blocks away from the present site. Our
recommendation was based on the following facts:
- The Office of State Architect has recommended
demolishing and replacing the current building;
- Caltrans will need to spend at least $70 million
for seismic retrofit and code upgrade improvements
to the current building and associated ramp structures;
- Since the existing terminal was not originally
designed as a bus terminal, it would probably
require tens of millions of additional dollars
for a major renovation to provide transbay bus
riders with the level of convenience that could
be available in a new facility;
- The existing building has an annual operating
deficit of approximately $1 million, which must
be defrayed with bridge toll revenue every year;
and the existing terminal does not meet the land
use and urban design objectives of the City and
County of San Francisco.
Relocation or replacement of the Transbay Terminal
continues to be a legitimate long-term regional
objective which we support. Nonetheless, the region
is not in a position to reach consensus on a new
terminal due to the current stalemate between San
Francisco officials -- who support relocation --
and East Bay officials, including AC Transit --
who oppose relocation. Moreover, the proposed new
terminal has an estimated capital cost of $140-170
million (depending on the number of bus decks)
which is not fully funded even if BATA were to
commit up to $80 million in toll surcharge funds
as requested by San Francisco.
We recommend deferring a decision on the Transbay
Terminal until the conditions set forth in the
following recommendation are met. If the Task Force
and BATA approve our recommendations on bridge
design and bicycle/pedestrian access, there will
be up to $89 million in remaining toll surcharge
funds available for the terminal project at a future
date.
3. A decision on relocating or replacing the Transbay
Transit Terminal should be deferred until such
time as sufficient consensus has been achieved
in support of relocation or replacement of the
current facility and a complete financial plan
has been developed for the supported option.
Other Bridge Design Issues
The fourth and fifth staff recommendations have
no effect on the toll surcharge extension, but
reflect important design issues for the new eastern
span. The fourth recommendation comes from EDAP
and concerns the design of the piers supporting
the new bridge. One of the recommendations approved
by the Commission last July requested that Caltrans
and the design team explore the possibility of
submerging the pile caps (at the base of the piers)
below water to improve visual appearance. After
further analysis by Caltrans and the design team,
EDAP now recommends for cost, safety, and other
reasons that the pile caps should be placed above
water -- as is the standard practice in bridge
construction -- but with careful attention to design.
The final staff recommendation arises out of a
number of unresolved bridge design issues identified
by EDAP, the City of Oakland, and others that warrant
close scrutiny in the post-30% phase of design.
Specifically, we recommend that the Task Force
provide continuing oversight for the remaining
bridge design phase with respect to the issues
outlined in the fifth recommendation below.
4. The pile caps for the piers supporting the
causeway section of the new bridge should be placed
above water, but with careful attention to the
design.
5. The Bay Bridge Design Task Force should provide
continuing design oversight of the remaining design
phase for the new eastern span including, but not
limited to, the following key issues: the Yerba
Buena Island transition and possible replacement
ramps, the design of the causeway section of the
bridge, and the Oakland touchdown.