![]() |
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
BAY BRIDGEMTC Bay Bridge Rail Feasibilty StudyCHAPTER 3. STRUCTURAL FEASIBILITY ANALYSIS The structural impact of rail transit on the Bay Bridge is dependent on the type of rail system selected. Figure 3-1 shows the system weight and clearance envelope required for each alternative rail system. The current Caltrain system has also been included for comparison. FIGURE 3-1: RAIL SYSTEM WEIGHT
AND CLEARANCE DATA
The train cars in the first systems are individually powered. The Amtrak Acela and Caltrain have locomotives powering the train sets that are considerably heavier. The higher locomotive loads may control the final design of some bridge components but, for this study, the main length of the train sets, the passenger cars, are the basis of comparison. It is important to note that all of the technologies considered for Transbay rail service are electronically powered. BART's electric power is via a third rail alongside the rails for the vehicle wheels. The other three systems access electrical power from overhead wires referred to as catenaries. Diesel fueled systems were not considered appropriate for this crossing due to the likelihood of an indoor stop at the current or reconfigured Transbay Terminal in San Francisco. While diesel buses do use the terminal, their operation allows for easy engine stopping and starting during waiting times. The diesel locomotives used in train sets do not offer this capability. Any analysis of the impacts of rail on the Bay Bridge requires three separate analyses:
WEST SPAN STRUCTURAL
COMPONENT DEAD AND LIVE LOAD PERFORMANCE - SEISMIC
RETROFIT AND NO RAIL Figure 3-2 contains the D/C ratios for the main elements of the superstructure. Note that these are the service load demands. The "1959 Reconstruction" numbers come directly from the 1965/67 investigation calculations. The "1999 Current" numbers reported are determined by factoring the dead and live load demands from the 1965/67 demands by the increase or decrease in loads. FIGURE 3-2: RETROFITTED WEST SPAN DEMAND TO CAPACITY RATIOS (ASSUMES NO RAIL)
These values are a worst case scenario for members in each category. These numbers in no way signify that each diagonal for the "Seismic Retrofit" scenario will require strengthening. Rather, the worst case will be to increase the strength of only a few members by 12% and the remainder by less or not at all. In very general terms, a 10% increase in total load would likely be tolerated for service load conditions. However, more in-depth analysis is required to determine the structure's tolerance to added loads. LOCATION OF RAIL SERVICE
ON THE WEST SPANS
1. Below Deck
FIGURE 3-3: BELOW DECK OPTION
Figure 3-4 provides a simulation showing how the bridge might look looking east from San Francisco. In this option, it would also be possible to run rail service on the lower deck of the bridge and to use the lanes below the bridge for auto traffic. Such a design would reduce the headroom required for the new deck, but would not substantially alter the structural impacts of the alternative at this level of analysis. If two directions of rail service are placed on the bridge deck in any alternative, a minimum of three lanes of traffic would be displaced. The remedial action would be to replace at least three traffic lanes above, below or beside the West span stiffening truss. The option of adding structure below the existing deck requires at least some reduction in the clearances for shipping. The United States Coast Guard must approve any reductions in vertical clearance. Preliminary indication is that they would be very concerned about reductions in clearance due to the placement of a radio beam for navigation and because vessels continue to get larger over time. This issue would need considerable attention in further studies. Lower Side by Side While either of the side-by-side rail options have some advantages, a key problem is that they are unable to drop down to the basement level of Transbay Terminal, which is the preferred location for a rail station, connecting Peninsula service to downtown and the bridge. Upper Side by Side NON-STRUCTURAL CONSIDERATIONS FIGURE 3-9: NON-STRUCTURAL CONSIDERATIONS - RAIL ON WEST SPAN
WEST SPAN STRUCTURAL COMPONENT DEAD AND LIVE LOAD PERFORMANCE - WITH RAIL, STRENGTHENING AND SEISMIC RETROFIT While the location of rail on the bridge would ultimately be an important consideration in a more detailed structural analysis, the three location options were not independently analyzed at this feasibility stage. Load Impacts of Rail on the West Spans FIGURE 3-10: LOAD IMPACTS OF RAIL ON THE WEST SPANS
Although there is some weight variation among the four rail technology options, any one of these options would have a negative impact on the main span and side spans of the Bay Bridge. The changes in load values on these elements is seen in Figure 3-11, assuming a uniformly distributed load. The figure shows that loads on the main span would increase by between 55% and 61%, depending on the technology selected. FIGURE 3-11: LOAD IMPACT
OF RAIL SYSTEMS ON BRIDGE SPANS
![]() Using the structural capacities discussed previously and the loading capacity required for the four rail systems, it is possible to develop demand/capacity ratios for key structural members with each of the four rail technology options. FIGURE 3-12: DEMAND/CAPACITY
RATIOS FOR WEST SPAN MEMBERS WITH RAIL AND ADDED DECK
AREA
As expected with such large load increases, the structure would require strengthening. Note that the values shown in Figure 3-12 do not suggest that rail is infeasible, they do suggest that significant effort will be required to avoid impacting the main cables. Insufficient capacity in the main cable is one of the greatest strength obstacles to overcome in a suspension bridge. Adding rope to strengthen the existing main cable is usually complicated by protective cable wraps, suspender saddle, tower saddle and anchorage constraints. When all other solutions are exhausted, adding a second set of cables is an option. The following section briefly describes alternatives that could reduce structural weight and therefore lower demand. Options to Reduce Structural Demand FIGURE 3-13: WEIGHT REDUCTION
POTENTIAL OF LIGHT WEIGHT ROADWAY DECKS
To provide a protective wearing surface for the concrete slabs on the West spans, Caltrans has installed a 3/4-inch epoxy overlay. For the proposed deck systems, this report assumes an equivalent surfacing. Fully developed deck designs could increase or decrease this thickness. The resulting change in added load would not change the conclusions of this feasibility study. Combining the weight savings of the deck options presented above with the loads from the various rail options changes the load impacts of rail on the main cable as seen in Figure 3-14. The range of load increase on the main cable and suspender cables, assuming an orthotropic steel deck, can be reduced to an increase of between 25% and 31%, depending on the technology selected. It should be noted that no significant study has been completed to determine the life-cycle implications of using an alternate decking material on the Bay Bridge Roadway. FIGURE 3-14: WEIGHT IMPACTS
OF RAIL OPTIONS ASSUMING LIGHT WEIGHT DECKING MATERIAL Revised demand/capacity ratios with various decking options are shown below: FIGURE 3-15: IMPACT OF LIGHTWEIGHT DECK MATERIAL ON
MAIN CABLE DEMAND
FIGURE 3-16: IMPACT OF LIGHTWEIGHT DECK MATERIAL ON SUSPENDER CABLE DEMAND
The figures show that while demand/capacity ratios are improved, the amount of weight savings is insufficient to eliminate strengthening or supplementing the main suspension cables. West Span Seismic Considerations
The added structure for two rail tracks would certainly alter these characteristics of the seismically retrofitted West spans. Adding rail would result in the following changes:
Some benefit may be derived from the rail scenario that widens the deck and adds tower legs and cables. With the added weight of the deck, foundation improvements are likely, as are tower leg improvements. By widening the piers and foundations to fit the new tower legs, much of the work can be designed to resist the added seismic demands. Likewise, up at the tower level, properly detailed connections between the existing and new tower legs offer opportunities to protect the existing towers from increased seismic demands. THE IMPACT OF RAIL OPERATIONS ON THE PROPOSED EAST SPANS The Proposed East Spans The width of bridge is sufficient to allow for an additional lane with rail although the design does not provide for the needed structural capacity. Geometrically, there is sufficient space to have five lanes and no shoulders, provided a lane width of 11'10" is acceptable to the reviewing agencies. As reported earlier, the West spans currently operate with 11'7" lane widths. The potential East span 11'10" lanes could possibly win approval from Caltrans. Also, depending on which train set is used, the rail width could be reduced to allow for both greater lane width and/or additional narrow shoulder. Structural capacity must be added to accept this configuration. Load Impacts of Rail on the Proposed East Spans Percent increase in live load from the current East span criteria of 1,400 pounds per linear foot of rail and four lanes, compared to the heaviest bridge rail alternative and five lanes of traffic, is 27%. With the lightest rail option, it is an 8% increase. Again, using this simplified comparison is appropriate for the level of study reflected in this report. More accurate conclusions require detailed analysis to fully document the increased demands of each structural component. Greater opportunities to maintain the existing ramps and simplify rail and vehicle operations would exist if rail were moved to the exteriors of the East span decks. The main benefit is on the eastern side of Yerba Buena Island. Exterior tracks can be readily split off the main decks permitting many possible alignments through new tunnels in Yerba Buena Island. With alignment options available, placing track outside of the West spans remains an option and would permit keeping five lanes of traffic together in each direction on these spans. Figure 3-19 shows alignments for rail on the exterior dropping down to a bore below the existing roadway tunnel. Alignments that parallel the existing tunnel are shown in Figure 3-20. FIGURE 3-17: CURRENT PROPOSED
EAST SPAN TYPICAL SECTION - 5 LANE DESIGN FIGURE 3-18: CURRENT PROPOSED
EAST SPAN TYPICAL SECTION - 4 LANE DESIGN WITH LIGHT
RAIL FIGURE 3-19: RAIL ALIGNMENT
- EAST SPAN'S EXTERIOR RAIL TO BELOW THE YERBA BUENA
ISLAND TUNNEL FIGURE 3-20: RAIL ALIGNMENT
- EAST SPAN'S EXTERIOR RAIL TO EACH SIDE OF THE YERBA
BUENA ISLAND TUNNEL Currently, for the East spans, the suspension cable arrangement slopes inward from the connection at the exterior of the deck up to the central control tower as shown in Figure 3-21. Rail and catenary wire clearances required for all the train scenarios, except BART, would result in interference with the suspender cables unless the shoulders are reduced for the vehicles. Ideally, the deck needs to be widened to move the cables outward and provide the necessary clearance. FIGURE 3-21: EAST SPANS SECTION From a traffic perspective, the deck should also be widened to accommodate the full five lanes. The current design width is 59'4" which is greater than the 58'0" on the West Side. For proper 12'0" lanes and one-foot shoulders, the East span decks need to be widened by 2'8". YERBA BUENA TUNNEL Live load code requirements for the deck in the tunnel have remained unchanged since the 1959 reconstruction. The lower level is a reinforced concrete slab constructed on a grade. Placing rail on this structure should not require alterations to the lower level support system. Rail on the upper deck, however, would compromise the floorbeams as the load changes from 2,400 plf today to over 3,000 plf with three lanes and one track or 3,680 plf with two lanes and two tracks. These values are for BART, the lightest system. Reconstructing the tunnel to support the additional loads is not a reasonable option since construction could not occur without closing the bridge for extended periods of time. A more feasible option would be to create new rail tunnel bores for rail so that the existing tunnel remains undisturbed. Note that the limited length of Yerba Buena Island at the likely tunnel elevation would not permit rail to enter one side of the island under the existing tunnel and depart up alongside the existing tunnel. This requires that the rail alignments at both the east and west face of the island are either side-by-side or below, but not a combination. While either option is feasible, there are significant engineering concerns about an option that requires rail on the East spans to drop down to a new Yerba Buena rail tunnel located below the existing roadway tunnel. Immediately east of Yerba Buena Island, the bridge decks must transition from a side-by-side alignment to a stacked alignment to meet the double-deck roadway tunnel. The vertical and horizontal geometry is extremely tight to accomplish this weave. Splitting off rail would require ramping down and under the planned weave, which may not be possible in the limited distance available. Vehicle Access to Yerba Buena Island
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
info@mtc.ca.gov • Report Web site comments • Accessibility Information • Site Help Metropolitan Transportation Commission • 101 Eighth Street, Oakland, California 94607 This page was last modified Friday February 27, 2009 © 2013 MTC |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||